Port of Tauranga - Pipe Jack

Hamilton

IMG_1321.JPG
IMG_1323.JPG
IMG_1324.JPG
IMG_2336.jpg

Project Description

Port of Tauranga - Pipe Jack

The sheetpile pit was seven metres by ten metres and was made of eight metres clutched interlocking sheets.

The pit was reinforced with 200 x 400 whaler beams and was dewatered using a six inch vacuum pump and a range of dewatering spears.

The pit was constructed to sit a pipe jacking plant inside. The pipe jacking operation pushed three DN1950 concrete pipes 30 metres under three railway lines.

The sheets were driven using a 35 tonne excavator and a Movax sheet piler.

The pit was excavated using a five tonne excavator.

Technical Overview

Construct a sheetpile pit for a pipe jacking plant. The pipe jacking operation pushed three DN1950 concrete pipes 30 metres under three railway lines.

Tauranga City Council
Contract Value: $100000
Year: 2014
Location: Port of Tauranga